Institute for Crisis, Disaster, and Risk Management

Crisis and Emergency Management

Newsletter Website
return to mainpage

 

 

 

April 2004                                                                            Volume 6 - Number 3

 

 

 Related Sites:

 

 

 

 

 

 

 

 

 

Disaster Updates...

 

 


FEMA Review Of Eleven-Alarm San Jose, Calif., [1]

By Christel Fonzo-Eberhard

Fire Underscores Challenges Posed By Extremely Large-Scale Incidents

A technical examination of the worst fire in San Jose, Calif., history  with damages of more than $90 million was released by the Department of Homeland Security's Federal Emergency Management Agency (FEMA) on February 2004.  A copy of the full report can be found at http://www.usfa.fema.gov/fire-service/techreports/tr153.shtm .

According to the report, “the fire began at the 42-acre Santana Row construction site and was reported to 911. Less than 10 minutes after the initial call, there was a second call reporting roof fires about half a mile from the initial fire site. Eventually, 119 firefighters and 31 pieces of apparatus would respond to the construction site fire and 102 firefighters and 34 pieces of apparatus would respond to the secondary fire that burned through nearby residential units. A total of 11 alarms would eventually be dispatched to the fires.”

"It's widely recognized that communication systems were quickly overloaded during this extraordinarily large event," said U.S. Fire Administrator R. David Paulison -- "The call volume pushed the fire department's system to the brink, even with police department assistance, and the amount of radio traffic also exceeded the capabilities of the fire department's system."

The major findings and key issues of the report are as follows:

 

Issues:  Collapse Zones

Comments:  The Santana Row complex quickly became fully involved and posed a

significant potential for collapse. The incident commander established a

collapse zone around the perimeter of the complex and removed personnel and

apparatus out of harms way.

 

Issues:  Communications

Comments:  The initial incident rapidly progressed to five alarms and flying

embers ignited a number of buildings downwind that ultimately developed into a

separate, six alarm blaze. The two incidents generated a very heavy volume of

radio traffic, which is common during large-scale incidents, and quickly

overtaxed the city's radio system.

 

Issues:  Concurrent Incidents

Comments:  Within a two-hour period, the San Jose Fire Department was confronted

with two large-scale events that would over tax the capabilities of all, but the

largest of fire departments. During these two events, the Department also

responded to twelve EMS calls and four fires, which included a fire on the roof

of a high-rise building that had been ignited by the flying embers from the

Santana Row fire.

 

Issues:  Construction

Comments:  The building of origin covered approximately six acres and included

six floors and a basement. Each floor contained approximately 225,000 square

feet. The basement and the first two floors were constructed of reinforced

concrete. The outer perimeters of the first two levels were to have been used

for retail purposes and the remainder as parking. A third, but smaller, level

for parking was built upon the top of the parking structure. Additionally, there

were five separate, wood-frame residential structures, three stories in height.

The majority of the structures did not have sheet-rock installed at the time of

the fire.

 

Issues:  Exposures

Comments:  The fire spread to the Huff/Moorpark area when burning embers from

the Santana Row fire became airborne and ignited a number of wooden roofs in the

neighborhood, which was approximately one-half mile down wind.

 

Issues:  Incident Management

Comments:  A system for managing large-scale incidents must be in place and used

in order to successfully manage incidents of this magnitude. The system should

include provisions for the accountability of personnel and their continuing

safety.

 

Issues:  Fire Suppression Systems

Comments:  Upon completion, the complex would have been fully sprinklered, but

the systems were not operational at the time of the fire.

 

Issues:  Mutual Aid/Automatic Aid

Comments:  San Jose has a number of automatic aid agreements with its neighbors

and automatic aid was included in the assignments to the Santana Row fire.

Mutual aid agreements exist, but are more problematic because all mutual aid

companies must be dispatched manually because they are not programmed into the

City's CAD system.

 

Issues:  Pre-Incident Planning

Comments:  Planning is essential in the management of a large-scale incident,

which involves resources from multiple jurisdictions and that requires the

interaction of multiple agencies.

 

Issues:  Resources

Comments:  The Santana Row fire required the commitment of 119 firefighters and

thirty-one pieces of apparatus.  The Huff/Moorpark fire required the commitment

of 102 firefighters and thirty-four pieces of apparatus. Additional apparatus

and personnel were required to respond to the sixteen incidents that occurred

during the event as well as maintaining a reserve to ensure protection for the

city while the incidents were brought under control.

 

Issues:  Time of Day

Comments:  The two multiple alarm blazes occurred during the middle of the

afternoon, which resulted in the early detection of both incidents and may have

prevented injuries and the loss of life that could have occurred had the fire

occurred during the night when the residents of the Huff/ Moorpark area may have

been asleep. However, the incidents contributed to congestion of the afternoon

rush hour that not only inconvenienced motorists, but potentially delayed the

arrival of the multiple alarm companies.